Reconstruction and Safety Improvements

100% state funds will be used this fall to improve the existing rail-trail in the southern part of the County.

FirstEnergy (formerly Met-Ed) Rail-Trail Reconstruction Project

FirstEnergy will be paving the trail from the Wilhelm Avenue Bridge in South Lebanon Township to Cornwall Borough. In exchange, that portion of the trail will be closed for several months in 2023 until the utility lines and poles are replaced in the general area.

Phase 6

The Phase 6 alignment includes the future trail through the John E. Wengert Park across from the former Lebanon Catholic School complex (Phase 6A), Chestnut Street right-of-way, county owned land along the Hazel Dike to S. 22nd Street (Phase 6B), a partially relocated S. 22nd Street, a new bridge over the Quittapahilla Creek on S. 22nd Street, existing S. 22nd Street to US Route 422 with intersection safety improvements (Phase 6C) and Lebanon Valley Mall property (Phase 6D).
Phase 6A and Phase 6B will go out to bid in August as one project. Phase 6C is now fully funded and should go to construction in 2024 when design is complete. No funds are in place as of now for Phase 6D.

Phase 8

Phase 8 Alignment Determined: The preferred alignment is the former railroad bed from Long Lane to the Bunker Hill area. Future easement or acquisition discussions are well underway with numerous property owners.

Phase 10

Phase 10 north of US Route 22 to a connection to the trail system in Swatara State Park near Lickdale. Phase 10 will include 3.0 miles of rail-trail and a connection to Pine Tree Road in Union Township. Phase 10 will be broken into two projects … 10A and 10B.

Phase 10A and 10B Design: State and local funds are being used to design the rail-trail from north of US Route 22 to a connection to the trails in Swatara State Park at Lickdale.

Phase 10A Construction Project: A state grant application is pending for the construction of Phase 10A from north of US Route 22 to Pine Tree Road, a distance of 0.60 miles in Union Township. This project should go to construction in 2024.

Phase 10B from Pine Tree Road to a Connection with the Trails in Swatara State Park: If we get a federal transportation earmark this fall, we will have all of needed funds and right-of-way for Phase 10B (2.40 miles). The project could go to construction in 2024.

Inwood Spur

The County and LVRT, Inc. are also exploring the possibility of building a spur trail from the new vehicular bridge at Inwood south along the east side of Swatara Creek to the county park where the historic truss bridge is now located.

LVRT, Inc. Tractor & Shed Grant Application

A new tractor and larger shed was another recent state grant application for state funds matched with LVRT, Inc. private funds.

Updated on June 23, 2022